Challenge

To identify and acquire mirror Data Centre site more than 50km from the primary site to comply with Financial Regulations and support EMEA network. It was deemed uneconomic to upgrade the existing infrastructure.
 

Solution

  • Working in collaboration with Corporate Solutions, we reviewed the available opportunities and provided a report on shortlisted options.
  • Agreed technical requirements in respect of power/cooling loads.
  • Completed due diligence on selected site and agreed legal documentation.
  • Provided project management services to monitor the landlord's upgrade works.
 
Results
  • Acquired existing 20,000 sqft Data Centre.
  • Terms agreed in line with recommendations.
  • Migration complete prior to lease expiry at existing site.
 
Michael Pullen, Marsh & McLennan commented:
 
“Data Centre transactions are never quick or simple, but Jones Lang LaSalle really worked hard to pull all the parties together, and persevered throughout the transaction to make sure that everybody met the time parameters agreed, to bring this through to a very successful conclusion for all concerned.”
 

All Case Studies

 

 

West Marsh Re-surfaces – regeneration for P&O Estates/united-kingdom/en-gb/case-studies/10/west-marsh-re-surfaces-regeneration-for-p-o-estatesWest Marsh Re-surfaces – regeneration for P&O Estates
Petroplus (Insurance Valuation)/united-kingdom/en-gb/case-studies/100/petroplus-insurance-valuationPetroplus (Insurance Valuation)
Acquisition for European independent broker/united-kingdom/en-gb/case-studies/102/acquisition-for-european-independent-brokerAcquisition for European independent broker